消防工程施工步驟:
一、 施工前(qian)準備成立(li)項目組
1、項目部(bu)了解工(gong)程概況(kuang)、圖紙會審,審定最佳施工(gong)方案,依(yi)據土建大計(ji)劃確定我方工(gong)期、進度計(ji)劃及用(yong)工(gong)計(ji)劃;
2、制定材(cai)料計劃,依據工(gong)(gong)程(cheng)進(jin)度及施工(gong)(gong)圖(tu)紙,合(he)理提供現場(chang)實際(ji)用量計劃,抄送采購(gou)部(bu);
3、項(xiang)目主管接觸建(jian)設及(ji)監(jian)理單位(wei)辦(ban)理一切開(kai)工手(shou)續(遞(di)交資質、組織(zhi)設計、開(kai)工報告(gao)等);
4、組織(zhi)施工(gong)人員(yuan)進場,進行(xing)安全教育及技術交底。
二、施工工藝流程
1、質安部全程檢查
(1)、消(xiao)(xiao)防(fang)水系(xi)統 組織項目(mu)成員→熟悉(xi)圖(tu)紙→施工(gong)(gong)(gong)(gong)資質、組織設計、開工(gong)(gong)(gong)(gong)報(bao)(bao)告,進(jin)場安(an)全教育、技術交底、編(bian)制計劃→鋼管(guan)(guan)(guan)(guan)進(jin)場報(bao)(bao)驗(yan)(yan)(yan)→預留孔洞尺寸核查→支吊架制作安(an)裝→管(guan)(guan)(guan)(guan)道(dao)除銹刷(shua)油→主管(guan)(guan)(guan)(guan)道(dao)安(an)裝→鋼管(guan)(guan)(guan)(guan)檢驗(yan)(yan)(yan)批(pi)(pi)、隱蔽工(gong)(gong)(gong)(gong)程報(bao)(bao)驗(yan)(yan)(yan)→支、配管(guan)(guan)(guan)(guan)安(an)裝→閥(fa)門(men)、消(xiao)(xiao)火栓進(jin)場報(bao)(bao)驗(yan)(yan)(yan)及閥(fa)門(men)強(qiang)度(du)嚴密性試(shi)驗(yan)(yan)(yan)→閥(fa)門(men)、消(xiao)(xiao)火栓安(an)裝→閥(fa)門(men)、消(xiao)(xiao)火栓檢驗(yan)(yan)(yan)批(pi)(pi)報(bao)(bao)驗(yan)(yan)(yan)→噴頭進(jin)場報(bao)(bao)驗(yan)(yan)(yan)→噴頭安(an)裝→穩(wen)壓裝置、水泵(beng)(beng)、水泵(beng)(beng)接合器進(jin)場報(bao)(bao)驗(yan)(yan)(yan)→穩(wen)壓裝置、水泵(beng)(beng)及水泵(beng)(beng)接合器安(an)裝→水泵(beng)(beng)接合器檢驗(yan)(yan)(yan)批(pi)(pi)報(bao)(bao)驗(yan)(yan)(yan)→系(xi)統調試(shi)→管(guan)(guan)(guan)(guan)道(dao)強(qiang)度(du)嚴密性試(shi)驗(yan)(yan)(yan)、管(guan)(guan)(guan)(guan)道(dao)清洗消(xiao)(xiao)毒記錄、消(xiao)(xiao)火栓試(shi)射(she)記錄、管(guan)(guan)(guan)(guan)道(dao)通(tong)水試(shi)驗(yan)(yan)(yan)報(bao)(bao)驗(yan)(yan)(yan)→分部(bu)(子(zi)分部(bu))工(gong)(gong)(gong)(gong)程報(bao)(bao)驗(yan)(yan)(yan)→分項工(gong)(gong)(gong)(gong)程報(bao)(bao)驗(yan)(yan)(yan)→水泵(beng)(beng)聯(lian)動調試(shi)→竣(jun)工(gong)(gong)(gong)(gong)圖(tu)制作→工(gong)(gong)(gong)(gong)程自檢→整(zheng)改(gai)→自檢合格→報(bao)(bao)驗(yan)(yan)(yan)→檢測公(gong)司檢測合格→報(bao)(bao)驗(yan)(yan)(yan)→消(xiao)(xiao)防(fang)部(bu)門(men)驗(yan)(yan)(yan)收合格→工(gong)(gong)(gong)(gong)程移交→售后服務。
(2)、火災自動報(bao)警(jing)系統(tong)
組織項目成員→熟悉圖紙→施工資質、組織設計、開工報告,進場安全教育、技術交底、編制計劃→鋼管、橋架進場報驗→鋼管敷設(明敷鋼管防火處理)→鋼管、橋架檢驗批、隱蔽及分項工程報驗→穿引絲→橋架安裝及橋架內布線→線纜進場報驗→管內穿線→接線(焊錫)→管內穿線檢驗批及分項工程報驗→線路絕緣測試→絕緣電阻測試記錄報驗 →設備進場報驗→設備底座安裝→設備安裝→設備安裝檢驗批及分項、分部/子(zi)分部工程(cheng)報驗(yan)→系(xi)統調(diao)(diao)試→系(xi)統調(diao)(diao)試分項工程(cheng)報驗(yan)→點位(wei)布置(zhi)圖制(zhi)作→工程(cheng)自(zi)檢(jian)→整改→自(zi)檢(jian)合格→報驗(yan)→檢(jian)測公司檢(jian)測合格→報驗(yan)→消防部門(men)驗(yan)收合格→工程(cheng)移交→售后服務。
三、消(xiao)防工(gong)程(cheng)部自檢
1、消防水(shui)系統 檢測依據:DB64/T404-410-2005《消防系統(tong)質(zhi)量檢驗評(ping)定(ding)規(gui)程》、GB50261-96《自動(dong)噴(pen)水(shui)(shui)(shui)滅火系統(tong)施工及(ji)驗收規范(fan)》 檢測項(xiang)目:消(xiao)防水(shui)(shui)(shui)泵、水(shui)(shui)(shui)泵接合器、室(shi)外消(xiao)火栓、輸(shu)水(shui)(shui)(shui)管(guan)網、壓(ya)力、主(zhu)要(yao)設備、消(xiao)防水(shui)(shui)(shui)池、消(xiao)防水(shui)(shui)(shui)箱、氣壓(ya)給水(shui)(shui)(shui)裝置、報警(jing)閥組、水(shui)(shui)(shui)力警(jing)鈴、水(shui)(shui)(shui)流指示(shi)器、噴(pen)頭、系統(tong)聯動(dong)試驗。
2、火(huo)災自動報(bao)警系統 檢(jian)測依(yi)據:DB64/T404-410-2005《消防系統質量(liang)檢驗評定規程》、GB50166-98《火災自(zi)動(dong)報(bao)警系(xi)統施工及驗(yan)收規(gui)范(fan)》 檢測(ce)項目:配管(guan)、系(xi)統布(bu)線、探(tan)測(ce)器(qi)的安(an)裝、手動(dong)報(bao)警按鈕、火災報(bao)警控制器(qi)、樓層顯示(shi)器(qi)、消防控制室、系(xi)統聯動(dong)試驗(yan)以(yi)上兩項需自(zi)檢合格。
四、申報檢驗
1、 檢(jian)測公司檢(jian)測
2、 檢測合格
3、 申報消防部(bu)門驗收
4、 消防驗收合格
五(wu)、消(xiao)防驗收合格
1、 對用戶(hu)進行系統操作培訓(xun)受(shou)訓(xun)人員簽(qian)字確認(ren)
2、 移交相(xiang)關工程資(zi)料,準備決算資(zi)料,配合財務部(bu)做好工程款回收工作
3、 建立工程售后(hou)服務檔案對用(yong)戶進行跟蹤服務。